Berkeley County Government Seal Berkeley County Government Slogan

One Cent Tax Projects

One Cent, Makes Sense update

One Cent Makes Sense

On November 4, 2008, the voters of Berkeley County passed a one percent sales and use tax for "financing the costs of highways, roads, bridges, and other transportation-related project facilities, and drainage facilities related thereto." This tax will last for seven years and all the revenue generated will be used to construct roadway improvements including the projects listed in the approved referendum. Collection began the following May and the first revenue was received in October of 2009. As of July 2014, a total of $95,000,607.81 has been collected. At this rate, $133 million will be collected over seven years.

This site is dedicated to keeping Berkeley County citizens informed on the progress of projects being constructed with your transportation sales tax. The following graphic illustrates the stage the project has reached (highlighted) and/or completed (✔).

In Progress Pending

Stage
1
 

Stage
2
 

Stage
3
 

Stage
4
 

Stage
5
 

Stage
6
 
One Cent, Makes Sense road improvement
PROJECT DESCRIPTION:

The project consists of the paving and related improvements for Ambassador Avenue from the intersection with Cooper Store Road (S-8-16) to the intersection with Macio Road (S-8-1117). The project length is approximately 3620 linear feet.


Stage 1 - Pre-Design

The Pre-Design stage includes selection of the consulting engineer and negotiation of the design contract; field surveys; property and right of way research; utility investigations; and geotechnical investigations.

Stage 2 - Preliminary Design

During the Preliminary Design stage, the consulting engineer performs engineering design sufficient to produce preliminary roadway and drainage plans. Those plans are reviewed by the Engineering Department and comments are returned to the consulting engineer for revisions and refinement of the design.

Stage 3 - Final Design

In the Final Design stage, the consulting engineer incorporates comments from the Engineering Department and from regulatory agencies into detailed final roadway and drainage plans. The final plans contain roadway plans, profiles, cross sections, details, and construction quantities which can be used for right of way acquisition, permitting, and bidding for construction.

Stage 4 - Permitting

Depending on the location and type of project, as well as the scope of the project, permit applications are submitted for one or more of the following:

Stage 5 - Right-of-Way Acquisition

In cases where the project requires the acquisition of additional right of way and/or easements, the appropriate documents are prepared and distributed to the affected property owners. If property owners have questions about the documents or the project, they are encouraged to contact the Engineering Department or the consulting engineer. The timely return of the right-of-way documents is critical to the construction schedule.

Stage 6 - Construction

Bid documents are prepared and construction contractors are invited to submit bids to construct the project. Based on an analysis of the bid results, a recommendation is made to County Council for awarding the construction contract. The selected contractor begins construction, which typically continues for three to six months until completion.